Scaffold down.
roof finished
Friday, October 9, 2009
Tiling complete.
-- Posted from my iPhone
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
About Me
James Hole
I am 27 and building a three bedroom bungalow in West Sussex, which will be mine and Julie's first home.
View my complete profile
Subscribe Now: Feed Icon
Subscribe in a reader
Self Build
Lock Farm Blog
Bookmark or Share this
Blog Archive
►
2010
(2)
►
January
(2)
Windows in!
Back doors fitted
▼
2009
(41)
▼
October
(3)
Scaffold down.
roof finished
Tiling complete.
►
September
(7)
One side complete.
Roof end of first day tiling
Started laying today
Fully bumped out roof!
Roof halfway bumped out!
Felt and batten complete.
Roof felt and battening
►
August
(4)
More pic's
Pictures of the finished roof timbers.
Roofing gear arrived today!
Fascias and soffit
►
July
(7)
Roof
9x2 A frame's at south end of building. The colla...
Time-lapse of roof construction (part 1)
Videos of the stages of the Foundations.
Second day roof framing
First day on roof.
Wall plate in position ready for roof.
►
June
(6)
Interior walls nearly done
up to plate level with lintels in place
Scaffolding going up for lift to plate level.
Brickwork progress and flint.
►
May
(2)
Beams in place blocks going in today after NHBC in...
Posted from my iPhone
►
April
(5)
Retaining wall
Finished
The Pour.
The Concreting
Groundbeam complete day before concrete
►
March
(3)
Finished the digging.
Updated pics of the groundbeam
Half way through the ground beam.
►
February
(4)
Reinforcements
Last day of piling
The piling.
The before photos.